|
Boiler
Hydrostatic Testing
The equipment
should have been hydrostatically
tested to a minimum of 1½ times
the design pressure, in the
factory, and copies of the
Manufacturer's Data report,
signed by the Authorized
Inspector witnessing and
evidencing the test forwarded to
all jurisdictional bodies as
well as to the Client. However,
the complete system, along with
all interconnecting piping,
should be hydrostatically tested
before start-up to comply with
code requirements and to check
for leaks that may have occurred
during shipping and handling.
This test should be completed
under the supervision of and
witnessed by an Authorized
Inspector who should represent
the State or municipality having
jurisdiction or the insurance
company covering the
installation. At the option of
this inspector, the hydrostatic
test may be at 1½ times the
design pressure of the
equipment, or at a pressure
slightly less than the setting
of the lowest safety valve. The
latter test will avoid the
necessity of blanking or gagging
of safety valves, removing
piping and plugging various pipe
openings, removing controls and
gage glasses, etc
The boiler and
process lines must be completely
vented in order to fill them
with water. The following is a
recommended procedure for
hydrostatic testing:
1. Open the
steam drum vent valve and gag
the safety valves in accordance
with safety valve manufacturer's
recommendations. In lieu of
gagging, the safety valves may
be removed and replaced with
test plugs or blind flanges.
2. Open the
vents on the interconnecting
piping. Close steam outlet
valve.
3. Isolate
pressure switches, gauge glasses
or control components that are
not intended to be subjected to
a hydrostatic test.
4. Fill the
system with treated water in
accordance with recommendations
from the Clients water treatment
consultant. (Refer to section
entitled "Water treatment
Considerations".
The test water temperature range
must be 70°F minimum to 120°F
maximum (100°F to 120°F water
temperature is preferred). Care
should be taken so that all air
is vented while the equipment is
being filled. Fill the equipment
until water overflows the vent,
then close the vent.
5. Apply
pressure slowly. The recommended
rate of pressure increase is
less than 50 psi per minute.
Proper control must be
maintained so that pressure does
not
exceed the
desired setting of the local
steam boiler inspecting agency.
Do
not subject any pressure part to
more than 1½ times the design
pressure rating of any component.
6. When the
proper test pressure is reached,
inspection in accordance with
the test objective can begin.
Examine the system for any
leaks. If no leaks are visible,
hold the
system in a pressurized static
condition for a period long
enough to satisfy the code
requirement.
7. Upon
completion of the test, release
pressure slowly through a small
drain valve. Then fully open
vents and drains when the
pressure drops to 20 psig.
Particular
Care must be
given to make sure that parts
not normally containing water
during Operations are drained
free of water. The system should
be drained fully after
hydrostatic
testing, to prevent freezing, if
the unit is installed in a cold
weather area, and to minimize
corrosion of the metal surfaces.
8. If
temporary hand-hole or man-way
gaskets were used for the test,
they should be replaced with
regular service gaskets before
readying the unit for operation.
Gaskets should
never be reused. Replace gage
glass if necessary and make sure
that the gage cocks are open.
Remove
all blanks or gags from safety
valves and install relief
valves, if removed.
9. Additional
inspection at this time by the
Authorized inspector will
determine whether the
installation including piping
arrangements, valve gauges and
controls
and other
equipment on the unit meets Code
and/or other jurisdictional
requirements.
10. Refer to
the "Summary of valve
positions" for recommended
positioning of the various
valves during hydrostatic
testing.
|