Suggested
Maintenance Log Program
The
following maintenance items, as
appropriate to the specific
boiler system, need to be
considered for implementation on
a regular basis (e.g., daily,
weekly, monthly, semiannually,
annually). A checklist of the
items should be incorporated
into a maintenance log with
provisions for checking off the
item for the appropriate period.
A separate log sheet is
suggested for each period. The
log sheets can be filed in a
loose-leaf binder, and should be
retained as a permanent
maintenance record.
The
log sheets can be used as a
handy check-off system when
establishing a facility
maintenance program. In all
cases the equipment
manufacturer's recommendations
should be followed.
DAILY
- Blow
down and test low water
cutoffs of steam boilers
(once per shift for high
pressure)
- Blow
down gage glasses (steam)
- Blow
down make up feeder (low
pressure steam)
- Blow
down boiler (steam)
- Check
boiler contraol linkage
- Check
boiler and system for leaks
- Check
burner flame
WEEKLY
- Check
compressor (s) lubricating
oil level (control and
atomizing)
- Check
flame signal strength for
both pilot and main flame,
and record readings
- Check
flame failure cutoff and
timing
- Check
pilot and main flame fuel
shutoff valve closing
- Check
ignitor and burner operation
- Check
level in chemical treatment
tank
MONTHLY
- Check
compressor (s) air filter,
and clean or replace as
required
- Check
boiler water treatment test
results received from
treatment company, adjust
treatment as required
- Lubricate
motor and equipment bearings
- Test
fan and air pressure
interlocks
- Check
main burner fuel safety
shutoff valves for leakage
- Check
low fire start interlock
- Check
high pressure/temperature
interlocks
- Test
low water cutoffs (hot
water)
- For
oil -- test pressure and
temperature interlocks
- For
gas -- test high and low gas
pressure interlocks
- Manually
lift safety/safety relief
valves and check operation
SEMIANNUALLY
- Inspect
burner components
- Check
flame failure system
components
- Check
piping and wiring of all
interlocks and shutoff
valves
- Recalibrate
all indicating and recording
gages and instruments
- Perform
a slow drain test for low
water cutoffs (steam)
- Check
combustion control system
- For
oil -- check atomizers and
strainers
- Test
boiler safety/safety relief
valves in accordance with ASME
Boiler and Pressure Vessel
Code, Sections VI and VII
ANNUALLY
- Perform
the SEMIANNUAL maintenance
procedures
- Check
all equipment coils and
diaphragms
- Perform
a pilot turndown test
- Recondition
or replace low water cutoff
- For
gas -- check drip leg and
gas strainer
- Clean
boiler firesides
- Drain
boiler, open manholes and
hand holes, and clean
watersides
- Have
boiler inspected by a
commissioned inspector
- Clean
burner and gans
- Replace
gaskets
- Leak-test
all fuel valves
- Test
operation of all controls
and safety devices
- Have
fuel-burning system adjusted
using combustion test
instruments
AFTER
EACH PERIOD
- Make
a record of all maintenance
and parts replacement in the
maintenance log
|