|
Boiler
Suggested
Shut-Down
When
the unit is taken out of
service, good care of the boiler
during the idle periods is
mandatory to prevent unnecessary
corrosion damage. Gradually
reduce load and run the fuel
system to low fire position.
When the unit is at the low fire
position, blow down the boiler
along with water column gage
glass and the feedwater control
valve. Following manufacturer's
recommendations, remove from
service all combustion
equipment. The until is to be
post purged with the fan for at
least 5 minutes and then allowed
to cool on natural draft after
removing the fan from the
service.
The
steam pressure should be allowed
to drop naturally without
opening vents or other
intentional means of taking
steam from the unit to hasten
the lowering of steam pressure.
A cooling rate exceeding 100°F
per hour to 150°F per hour by
excessive opening of vents
should be avoided to limit the
drum distortion and resulting
strains on tube joints. Vents
can be fully opened when the
steam pressure drops to 15 to 20
psig. Close the stop valve on
the steam line and open the
drain (if provided). When the
steam pressure has dropped to
approximately 20 psig, open the
drum vent valve to prevent a
vacuum from forming within the
boiler. The boiler is drained
only after the water temperature
drops below 200°F.
To
insure that the safety valves
are maintained in good working
order they can be hand lifted or
popped at periodic intervals. It
is recommended that the valves
be lifted just prior to a
planned boiler shutdown, as a
check to determine whether
repair work is necessary.
When
removing a boiler from service
for storage, inspection or
cleaning the circulation of
water ceases. This causes
suspended solids in the water to
settle out on the boiler
surfaces, cake and dry to an
adherent sludge, which can be
mistaken for scale during normal
operation.
Standby
Protection
Many
boilers used for heating or
seasonal loads or for standby
service may have extended
periods of non-use. Special
attention must be given to
these, so that neither waterside
or fireside surfaces are allowed
to deteriorate from corrosion.
Corrosion can be more serious
during this down time than when
the boiler is actually in
service. The key factors
responsible for corrosion are
water, oxygen, and pH.
Elimination of either moisture
or oxygen will prevent
appreciable corrosion.
Two
types of storage systems are
widely used; these are wet and
dry storage methods. Wet storage
is adopted for short duration
lay up and dry storage is used
for shut downs exceeding
approximately 30 days. No unit
should be wet-stored when the
temperature could drop below the
freezing point.
In
situations where the boiler is
"headered" with other
steam generating units it may be
possible to maintain the boiler
in idle storage by means of
treated blowdown water or steam
flooding from an operating unit.
If these alternate lay-up
methods are considered feasible
the Owner should assure that his
water treatment consultant firm
has reviewed the water chemistry
aspects of the alternate method
and agreed to it's
implementation as a means of
protecting against corrosion.
Wet
Storage
As
the boiler is being shut down
and as the pressure subsides,
but before steaming stops, add
chemicals to the boiler to
scavenge oxygen and to control
pH, per the recommendations of
the Owner's water treatment
consultant.
When
the boiler pressure gauge
indicates about 10 psig
completely flood the system with
deaerated treated water with the
drum vent open. Close the drum
vent after it begins to
overflow. The steam stop valve
should already be closed. Water
should be added through the feed
pump until 10 psig is maintained
as indicated by the drum
pressure gauge.
Close
the feedwater valves. Observe
the steam drum pressure gauge
and maintain pressure. If
pressure builds, it may be due
to leaking feedwater valves,
which may not be properly
seated. A pressure loss (after
the boiler is cool) indicates
leakage, so check all fittings
and valves for leakage.
Frequent
water samples should be taken
and analyzed by the water
treatment consultant. If the
analysis indicates a need for
additional chemicals, the level
in the boiler steam drum should
be lowered to normal level and
chemicals added. The boiler
should be then be steamed to
circulate the solution, and the
process of wet storage repeated
as previously described.
Close
all gas side access doors.
Isolate the system to prevent
cold air from reaching the
heating surface. Periodic
inspections of the external
surfaces of the pressure parts
should be made to guard against
condensation and subsequent
corrosion.
During
storage, steps should be taken
to protect the exterior
components from the possibility
of rust or corrosion. These
parts should be coated with a
rust inhibitor and protected
from moisture and condensation.
Electrical equipment should
likewise be protected. Keeping
the control circuit energized
may prevent condensation from
forming in the control cabinet.
Dry
Storage
When
the unit will be idle for a
considerable length of time and
a short period can be allowed to
prepare the boiler for return to
service, the dry storage method
is recommended.
1.
The unit should be cooled down
and then completely drained.
Make sure that no pockets of
water remain in the drum,
piping, water column, etc. Open
all vents t to assure complete
drainage.
2.
Open all the manways and
thoroughly wash the water side
surfaces to remove any sludge
deposits. Mechanically clean
residual particulate from the
gas side metal surfaces and
inspect the system thoroughly.
3.
Dry the system thoroughly. If an
air hose is used, be sure
condensate from the air tank is
not blown into the tubes and
that the air is oil free.
4.
Place flat wooden trays of
moisture absorbent, such as
quick lime or silica gel,
inside
the drums to absorb any moisture
that will be trapped when the
unit is
closed
up. The trays should be placed
on supports to allow air to
circulate under them. For
recommendations on quantity of
moisture absorbent, the Owner's
water consultant should be
contacted. The trays should not
be more than 3/4 full of the dry
absorbent to prevent overflow of
the corrosive liquid that has
been absorbed.
5.
After the entire system is dried
the boiler system should be
pressurized with nitrogen to
approximately 5 psig though the
drum vent. Close the steam
outlet, drain valves, and
feedwater block valves. Ensure
that the system has been purged
completely before pressurizing.
6.
Close all the openings to
prevent water, steam or air
leakage into the unit. Leave
open the code required drain
valve between the process steam
stop valves to prevent
back-leakage of condensate from
any downstream header that may
be pressurized.
7.
Isolate the boiler to prevent
moisture from reaching the
heating surface.
8.
Keep the boiler room dry and
well ventilated to reduce
possible surface corrosion.
|