What
Should You Do Before Starting
Boilers
After Summer Lay-up?
With
the fall heating season coming
upon us, it is a good time to
reconsider steps that need to be
taken prior to starting boilers
after a lay-up period. While
this list is not all-inclusive,
it can serve as a guide for
those responsible for boiler
operation.
Before
a boiler is placed in operation,
boiler operators and other
responsible personnel and/or
supervisors, must check over the
entire system and carefully
review operating procedures.
Operating
Manuals
All
manufacturers of boilers and
fuel burning systems supply
operating manuals with their
equipment. Unfortunately, many
boiler rooms do not have manuals
and operating instructions
available. These manuals have
either been lost or misplaced.
It is the responsibility of the
responsible supervisor to obtain
these publications and see
that they are read, understood,
followed and available in the
boiler room.
Maintenance
During Summer Lay-Up
The
summer shutdown period is a good
time to accomplish necessary
boiler and fuel burning system
preventive maintenance. A
suggested check list of such
maintenance follows:
- Drain
and flush the boiler, open
all handholes and manholes,
clean and remove soot and
scale from the firesides.
Examine the boiler for
damage and corrosion.
- Have
the boiler inspected by an
authorized inspector, as
required.
- Install
new gaskets, replace all
handhole and manhole covers,
refill boiler and perform a
hydrostatic test, if
required.
- Institute
a suitable boiler water
treatment program to reduce
scale buildup and corrosion.
- Have
the fuel burning equipment
cleaned and adjusted by a
competent service
technician. Verify operation
of all operating and limit
controls, interlocks and
gages. Have the technician
disassemble the low water
cutoff and water feeding
devices, clean, recondition
and reassemble them. Have
the technician leak test all
fuel safety shutoff valves.
- Lubricate
all mechanical equipment
such as fans and pumps,
verify motor rotation.
- Check
all boiler piping for leaks
and missing insulation
- Make
sure provision is made for
establishing and keeping a
boiler log.
Start-up
Checks
Immediately
prior to boiler start-up perform
the following:
- Check
that all ventilation and
combustion air openings and
louvers are clean and free
of debris.
- Verify
boiler water level.
- Check
that all stack dampers are
open.
- Examine
the boiler furnace for
foreign material.
- Check
the furnace and flue passes
for fuel accumulation.
- Make
sure the manual fuel valves
are open.
Normal
Start-up
After
completing the start-up checks,
close the operating switch and
commence the normal starting
sequence. The following list
suggests a typical starting
sequence:
- operating
controls closed
- interlocks
(safety controls) closed
- start
fans and purge the boiler
- purge
requirements met
- energize
igniter
- prove
ignition flame within 10
seconds
- energize
main fuel valve(s)
- establish
and monitor main flame
- deenergize
ignition, main flame proven
- release
firing rate (combustion)
control to demand
- normal
operation
This
starting sequence should be
carefully observed to make sure
that all steps are normal.
Readings on flame signal
strength meters (if fitted)
should be observed and recorded
in the boiler log.
A
normal shutdown should be
initiated by opening the manual
burner switch. After the post
purge has been completed, check
the furnace for flame cutoff and
make sure there is no residual
flame in the furnace. Have fuel
safety shutoff valves repaired
or replaced if required.
Additional
guidance can be found in the
boiler operating manuals and in
ASME CSD -1, Controls and Safety
Devices for Automatically Fired
Boilers, or in the National Fire
Protection Association's NFPA
8500 standards on prevention of
boiler furnace explosions.
|